Since the new millennium our hall has gone through a dramatic transformation from a building with limited function and future to one that  has form function and purpose. This has been achieved with a lot of support and encouragement by many organisations and individuals

After several years of false starts and over ambitious plans finally in 2000 the Neuadd got both permission and funding for a £350,000 refurbishment and extension.

This work involved re-roofing the existing hall, building an annexe with a kitchen, toilets and a small meeting room. 180 of the fixed seats were removed and the sloping area used for dances was levelled and a sprung maple floor installed. Stackable seating was purchased and the sound and lighting significantly upgraded facilities for those with disabilities were installed, including a wheelchair lift and an induction loop.

The time line looks like this :- 

2000 Refurbishment and building an annex to the hall circa £350K 

2009 We bought the building from Gwynedd Council.

2012 Building our community annex, funded by CFAP and others £370K

2014 Stage lighting Project Mainly Arts Council for Wales £22K

2015 Rebuilding the stage and stage grid, funded through Mantell Gwynedd £37K

2017 Resource Efficiency project phase 1 Mainly WEFO £158K this was the development of an energy audit and then various options to improve this. The main achievements were a ground source heating system for the main hall and air handling unit for the annex

2022 Resource Efficiency project phase 2 We were awarded £250K from Welsh Governments community facilities program to install a new aluminum roof with increased insulation and 27kw Bipvco solar PV panels Plus other minor projects.   

2025 We start planning the next phase. A retractable seating system an a modest extension Provisional Plans